077 - The Fire Dept cleaned the entire parking lot 078 - The first blackboard was monuted 079 - The second blackboard was mounted 080 - Vintage clock was mounted 081 - Map holder and maps installed
The Fire Dept
cleaned the en-
tire parking lot

The first
blackboard
was mounted
The second
blackboard
was mounted
Vintage clock
was mounted
Map holder
and maps
installed
082 - Financial audit for NYS was conducted 083 - The piano arrived 084 - Started to populate with student desks 085 - And we even populated with students 086 - Fully populated with student desks
Financial
audit for NYS
was conducted

The piano
arrived
Started to
populate with
student desks
And we even
populated
with students
Fully populated
with student
desks
087 - And the teachers desk 088 - Starting to dig drainage ditches 089 - We encountered many roots 090 - Removing shale from temporary driveway 091 - Backfilling trenches after pipes were installed
And the
teacher's desk
Starting to
dig drainage
ditches
We encount-
ered many
roots
Removing
shale from
temporary
driveway
Backfilling
trenches after
pipes were
installed