Schoolhouse #8
"Walk of Remembrance" Activities
page 1 of 4
Initial layout of
the Walk of
Remembrance
Sod was
stripped
Edging was
installed
Another 14
inches of
dirt removed
Tree roots were
a challenge
In went four
inches of slag
Slag was
well packed
Four inches of
sand was added
& packed
First 54 engraved
bricks arrived
The granite slabs
weigh around
120 pounds
Leveling and
re-leveling was
the procedure
First 12 bricks
in place
And then there
were 54 bricks
in place
And then there
were 108 bricks
in place
Many people
came to the dedi-
cation ceremony